Commercial Retrofit Top Ten… talking Risk, Value and Sequencing:

Commercial retrofit projects begin with a broad range of objectives and starting points. Worryingly, they are too often already exposed to significant cost and risk, on account of premature design decisions, unrealistic programme expectations and incomplete data. It doesn’t need to be like this!

The following 10 points will help each Retrofit journey start on the right footing:

1. The adage about, “the risk in construction is all in the ground”, isn’t true for modern Refurbishment/Retrofit – the biggest refurbishment/retrofit risks are almost always concealed.  Examples of these are problems with fire stopping, structural fire protection, slab edges, façade interfaces, services, historic penetrations and previous alterations.  These can all sit behind finishes and above ceilings.

2. Existing records may be incomplete, out of date or incorrect.  If your design is based primarily on record drawings and visual surveys, you are working with shaky assumptions.

3. Leaping to design freeze and construction is a risky strategy - and can lock in the wrong solution and sequencing.  As an example, discovering a major building-safety issue can trigger redesign across multiple disciplines, including layouts, MEP strategies, ceilings, and finishes, leading to extra cost & disruption.

4. The cost of investigation is comparatively small relative to the cost of redesign or reconstruction. The cost of opening-up works, intrusive surveys and targeted testing early in the process can avoid substantial abortive design, delay and change later.

5. Commercial offices are particularly vulnerable to historic cumulative change – the knock on of years of tenant fitouts, CAT A/CAT B works, service upgrades, riser modifications and maintenance interventions can progressively alter compartmentation and fire strategy.

6. Compliance cannot safely be inferred from appearance – a building that looks well maintained may still contain incomplete fire stopping, unprotected structure or undocumented changes.

7. Retrofit should start with diagnosis, not design. In short, establish a baseline - the actual condition of the building, understand its original strategy and subsequent alterations, then determine what should be retained, repaired, upgraded or replaced.

8. Life-safety issues can fundamentally change the investment case, and may affect occupation strategy, phasing, programme, insurance, landlord obligations.

9. Early investigation enables client choices. Problems identified before design is frozen can be prioritised, costed and incorporated intelligently rather than dealt with as late-stage surprises.

10. The objective is not to survey everything indiscriminately, but rather targeted investigation to reduce the major unknowns and make informed decisions…

Successful retrofit starts with diagnosis: understand the building beneath the 'skin' before shaping the investment.